Consider the following statements with respect to PERT and CPM1. PERT is a probabilistic approach and it is well suited for R D2. Project crashing is possible in a PERT network if cost elements are provided.3. Critical path duration will be the minimum time required to complete the project in a CPM network.Which of the above statements is/are correct?

No worries! We‘ve got your back. Try BYJU‘S free classes today!

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses

No worries! We‘ve got your back. Try BYJU‘S free classes today!

No worries! We‘ve got your back. Try BYJU‘S free classes today!

Solution

The correct option is B 1 and 3In PERT network, project crashing is not possible

Which of the following statements is not correct about pert?

| Which one of the following statements is not correct?

A. PERT is event oriented & CPM is activity oriented

B. CPM is event oriented & PERT is activity oriented

C. Both PERT & & CPM are used for project estimations techniques

D. In PERT, three-time estimates are made for each activity and is CPM only one-time estimate are made for each activity.

Please scroll down to see the correct answer and solution guide.

Right Answer is: B

SOLUTION

PERT and CPM are the two network-based project management techniques, which exhibit the flow and sequence of the activities and events.

PERT

CPM

i) Event oriented

i) Activity oriented

ii) Three time estimates

ii) One time estimate

iii) Probabilistic Activities

iii) Deterministic activities

Related Questions

10 Questions  |  By Sihemsmida | Last updated: Mar 22, 2022 | Total Attempts: 27017

Which of the following statements is not correct about pert?
Which of the following statements is not correct about pert?
Settings

Feedback

During the Quiz End of Quiz

Difficulty

Sequential Easy First Hard First

Which of the following statements is not correct about pert?

Are you familiar with PERT and CPM? Do you think you can pass this quiz? PERT and CPM are two network-based project management techniques that demonstrate the activities and events' flow and order. PERT stands for Project Management and Review Technique, whereas CBM stands for Critical Path Method. They are frequently used in research development projects. If you want to learn more about PERT and CPM, these PERT And CPM Quiz Questions with answers are for you.


  • 1. 

    CPM is:

    • A. 

      Critical Project Management

    • B. 

      Critical Path Management

    • C. 

      Critical Path Method

    • D. 

      Crash Project Method

  • 2. 

    Which of the following statements is not correct?

    • A. 

      PERT is probabilistic in nature.

    • B. 

      CPM is probabilistic in nature.

    • C. 

      CPM and PERT use similar terminology but were developed independently

    • D. 

      .All of these statements are correct

  • 3. 

    Mark the wrong statement:

    • A. 

      A project is a set of activities that can be performed in a certain logical sequence.

    • B. 

      A network is a graphic portrayal of the independency relationship among the activities of a project.

    • C. 

      An arrow representing an activity can have any length and shape.

    • D. 

      An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.

  • 4. 

    Which of the following is not a rule of network construction?

    • A. 

      Each defined activity is represented by one and only one arrow.

    • B. 

      A network should have only an initial and one terminal node.

    • C. 

      Identical initial and final nodes can identify two activities.

    • D. 

      Only as few dummy activities should be included as is warranted.

  • 5. 

    Mark the wrong statement.

    • A. 

      Forward pass calculations yield the earliest and the latest start and finish times of various activities.

    • B. 

      The difference between the latest and the earliest finish times is the total slack.

    • C. 

      Backward pass determines the latest start and the latest finish.

    • D. 

      Determination of the earliest and the latest start time of various activities of a project is useful for proper planning of their execution.

  • 6. 

    Mark the wrong statement.

    • A. 

      All activities on a critical path are critical activities.

    • B. 

      A project network may have none, one, or more critical paths.

    • C. 

      A delay in critical activity surely delays the completion of the project.

    • D. 

      Each critical activity has identical earliest and the latest start times.

  • 7. 

    Which of the following is not correct in respect of PERT calculations?

    • A. 

      The expected time of an activity is a weighted average of three times estimates, a, m, and b, with respective weights of 1, 4, and 1.

    • B. 

      The target time minus the expected time divided by standard deviation is the z value

    • C. 

      The completion of the project using the PERT method follows a normal distribution.

    • D. 

      The sum total of variances of critical activity times gives the variance of the overall project completion time.

  • 8. 

    Given, expected duration of the project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days? Z       :   0.33           1.0 Area  :   0.1293       0.3413

    • A. 

      0.6293

    • B. 

      0.8413

    • C. 

      0.1587

    • D. 

      0.3707

  • 9. 

    Given, expected duration of the project = 47 days, variance = 9 days. Expected Time for Project Completion: 50 days Z:   0.33           1.0 Area:   0.1293       0.3413 What is the probability of completing the project within three days, more or less than the expected time?    

    • A. 

      0.5000

    • B. 

      0.6826

    • C. 

      0.2586

    • D. 

      0.3174

  • 10. 

    Mark the wrong statement.

    • A. 

      An event that represents the initiation of more than one activity is called the burst event.

    • B. 

      The longest path of a given project gives the maximum duration, while its shortest path indicates the shortest duration.

    • C. 

      The resource allocation programs aim to allocate the given resources in a manner that the project completes in minimum time.

    • D. 

      A non-critical activity may or may not have any free float.

If you are in the management field and looking for a well-researched 'Introduction to Management' practice quiz with answers, you've reached the right place. Management is the act of getting people together to pursue...

Questions: 10  |  Attempts: 43584   |  Last updated: Apr 10, 2022

  • Sample Question

    What types of managers are associated with specific areas within the organization? (Choose multiple)

    Which of the following statements is not correct about pert?

    Marketing managers

    Which of the following statements is not correct about pert?

    Financial managers

    Which of the following statements is not correct about pert?

    Operations managers

    Which of the following statements is not correct about pert?

    Human resource managers

    Which of the following statements is not correct about pert?

    Administrative managers

    Which of the following statements is not correct about pert?

    Top managers

Do you have good knowledge about Front office hotel management? Take this Front office quiz and see how well you can score. The questions are simple and interesting to check your knowledge about various terminologies,...

Questions: 47  |  Attempts: 34909   |  Last updated: Mar 22, 2022

  • Sample Question

    Which department receives orders to deliver food and beverages to the guests' rooms?

    Which of the following statements is not correct about pert?

    Housekeeping

    Which of the following statements is not correct about pert?

    Front Office

    Which of the following statements is not correct about pert?

    Room Service

    Which of the following statements is not correct about pert?

    Food and Beverage

Do you know the meaning of Integrated Management Of Childhood Illness? Do you have a good understanding of this subject? Here is an 'Integrated Management of Childhood Illness (IMCI) Quiz' that is designed to test your...

Questions: 29  |  Attempts: 34841   |  Last updated: Mar 22, 2022

  • Sample Question

    You can classify that a child aged 2 years has fast breathing if he has a respiratory rate of _________.

    Which of the following statements is not correct about pert?

    60 bpm or more

    Which of the following statements is not correct about pert?

    50 bpm or more

    Which of the following statements is not correct about pert?

    40 bpm or more

    Which of the following statements is not correct about pert?

    Any of the above

More Management Quizzes

  • Accounting Quizzes
  • Advertising Quizzes
  • Agriculture Quizzes
  • Automotive Quizzes
  • Brand Quizzes
  • Business Accounting Quizzes
  • Business Analyst Quizzes
  • Business Development Quizzes
  • Business Environment Quizzes
  • Business Etiquette Quizzes
  • Business Finance Quizzes
  • Business Math Quizzes
  • Business Organization Quizzes
  • Business Plan Quizzes
  • Business Process Quizzes
  • Business Study Quizzes
  • Business Technology Quizzes
  • Ceo Quizzes
  • Collaboration Quizzes
  • Company Quizzes
  • Construction Quizzes
  • Consumer Quizzes
  • Csr Quizzes
  • Customer Quizzes
  • Customer Service Quizzes
  • Development Quizzes
  • Ecommerce Quizzes
  • Employment Quizzes
  • Entrepreneurship Quizzes
  • Finance Quizzes
  • Hospitality Quizzes
  • Human Resources Quizzes
  • Industry Quizzes
  • International Business Quizzes
  • Introduction To Business Quizzes
  • Investment Quizzes
  • Logistics Quizzes
  • Manufacturing Quizzes
  • Marketing Quizzes
  • Material Quizzes
  • Media Quizzes
  • Office Quizzes
  • Organization Quizzes
  • Principles Of Business Quizzes
  • Printing Quizzes
  • Product Quizzes
  • Publishing Quizzes
  • Real Estate Quizzes
  • Retail Quizzes
  • Sap Business One Quizzes
  • Small Business Quizzes
  • Source Quizzes
  • Supply Quizzes
  • Survey Quizzes
  • Telecommunication Quizzes
  • Trade Quizzes
  • Transportation Quizzes
  • Warehouse Quizzes
  • Welding Quizzes

+ Show more

Which of the following statements is not correct about pert?
Back to top

Which of the following statement is correct PERT is deterministic?

Answer» b. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.

Which of the following is characteristic of PERT?

PERT uses event oriented Network. Estimate of time for activities is not so accurate and definite. It is used mostly in research and development projects, particularly projects of nonrepetitive nature. The probabilistic model concept is used.

What is a PERT Mcq?

Programs or Project Management and Review Technique (PERT) is appropriate for those projects where the time required to accomplish different activities are not known. CPM or Critical Path Method is appropriate for the projects that are reappearing (recurring) in nature.

Which of the following is a basic assumption of PERT?

The main PERT assumptions are given along the following lines: The activity durations are independent random variables. The critical paths are independent (i.e. have no activities in common) The normal distribution can be applied (n is sufficiently large) thanks to the central limit theorem.